Hydro Shield L35 and L45 installation - illustrated guide

Installation guide

Hydro Shield Large L35 / L45

Hydro Shield mounts on the motor's skeg below the propeller. This guide covers installation with and without power trim, using the manufacturer's dimensions and illustrations.

Estimated installation time: 20-30 minutes.

Download PDF in English

Package contents

  • 1 Hydro Shield hydrofoil
  • 2 brackets in 316 stainless steel
  • 4 stainless steel carriage bolts
  • 3 stainless steel truss-head screws
  • 7 Nyloc locking nuts

Tools required

  • 7/16-inch spanner
  • Drill and 1/4-inch drill bit (6.35 mm)
  • Clamp
  • Phillips screwdriver
  • Tape measure
  • Ruler or straightedge
  • Optional: urethane sealant

1. Choose the installation type

With power trim

Use this setting when the boat has power trim and the motor is trimmed out at speed.

D = A + 1/2 inch (12.7 mm)

Minimum clearance: 1 7/8 inch (approx. 48 mm)

Between the propeller and the trailing edge of the Hydro Shield foil.

Without power trim

Use this setting when the boat has no power trim and the motor remains in a fixed position.

A = D

Minimum clearance: 1 7/8 inch (approx. 48 mm)

Between the propeller and the trailing edge of the Hydro Shield foil.

2. Attach the brackets to the foil

Attach the brackets to the foil using the carriage bolts and Nyloc nuts. Leave the nuts loose enough for the brackets to move slightly. Tighten them fully during the final tightening in step 9. Keep pressure on the carriage-bolt heads so they do not drop and damage the foil's internal locking collar.

Bracket and foil assembly
Illustration key: 1: L bracket · 2: R bracket · 3: Locking nut · 4: Carriage bolt · 5: Foil

3. Position the assembly on the skeg

Place the brackets and foil on the motor's skeg. Align the leading edges of the brackets and skeg. The brackets must not protrude beyond the leading edge of the skeg. If the skeg is bent, bend the brackets to fit without bending the skeg.

Positioning the brackets on the skeg

With power trim, the upper part of the bracket's front edge sits farther aft than the lower part.

4. Check alignment and clearance

Use a tape measure to check A and D. Follow the setting for your installation type below. Rotate the propeller and check the minimum clearance before drilling.

With power trim

With power trim: D must be 1/2 inch (12.7 mm) greater than A. The minimum clearance from the propeller to the foil's trailing edge is 1 7/8 inch (approx. 48 mm).

A and D measurements with power trim
Illustration key: 1: Anti-ventilation plate · 2: Leading edge of skeg · 3: Leading edge of L bracket · 4: Bottom of skeg · 5: Leading edge of propeller · 6: Leading edge of Hydro Shield

Without power trim

Without power trim: A and D must be equal. The minimum clearance from the propeller to the foil's trailing edge remains 1 7/8 inch (approx. 48 mm).

A = D

A and D must be equal.

1 7/8 inch (approx. 48 mm)

Between the propeller and the trailing edge of the Hydro Shield foil.

Rotate the propeller and check clearance.

Original manufacturer illustration; not to scale.

Extend the planing line of the L-bracket flange with a ruler or straightedge. Use this extended line when measuring A and D, as shown in the illustration.

5. Clamp the assembly in place

Once alignment and clearance are confirmed, use a clamp to hold the brackets and Hydro Shield in place.

Clamping Hydro Shield in place

6. Drill the first hole

Use the holes in the bracket as a template. Drill the upper rear hole first. Fit the truss-head screw and Nyloc nut.

Drilling the mounting holes

7. Recheck the measurements and drill the remaining holes

Recheck A and D and the clearance between the propeller blade and the foil's trailing edge before drilling the second upper hole. Fit the screw and Nyloc nut. Then drill the third hole and fit the screw and nut. If using urethane sealant, apply it only after confirming the fit by fastening the screws.

8. Remove excess screw threads

If the fitted screw threads extend beyond the Nyloc nut, cut off the excess threads to prevent cavitation, reduce drag and improve performance.

Removing excess screw threads

9. Tighten and check

Tighten all screws and bolts securing the brackets to the skeg and foil. Check that all Nyloc nuts are tight before using the boat. Check the tightness again after the first outing.

Choose the correct model

Use the model selector in our online shop, or contact us for help before ordering.

Choose a model for your boat Download PDF in English

Based on Hydro Shield's 2024 installation guide. Illustrations used with permission. Inch dimensions are retained; metric clearances are approximate conversions.

Questions about installation: Nordic Smart at nordicsmart.eu or the manufacturer at hydro-shield.com.

Edition: 24 October 2026